Medical Center Client
Texas

Renovating a Fully Operational
Data Center

Our client, one of the premier cancer treatment and research facilities in the nation, selected us to manage the construction of its data center renovation and expansion. The 19,000sf facility features two 5,000sf data centers (one renovated, the other module built by the project team), totaling 10,000sf of raised computer flooring (white space). The remaining 9,000sf consists of renovated security office, restrooms, a loading dock, one ADA aluminum ramp, one ADA concrete ramp, a sprinkler pre-action room, a new set of paralleling gear, PDUs and CRAC units.

The scope of the project consisted of upgrading the existing data center infrastructure and equipment, converting it to a near Tier III data center. Interior architectural modifications were required to support the new mechanical, electrical, and plumbing (MEP) infrastructure and offer additional protection and security. In order to keep our client’s existing data center operation running while the construction was underway, the project was divided into three phases. All equipment and systems were fully tested and commissioned to ensure proper functionality.

Infusion Therapy Clinic

The project entailed both demolition and fit-out 9,000sf for the new Infusion Therapy Clinic, which includes clinical and office space. The project scope included the build-out of the south half of the floor, including all architectural, mechanical, electrical, plumbing, and fire/life safety elements within an occupied floor of the hospital.


For More Information
John Clark
(713) 650.6420
Email John